It's been an exciting start to the year for us at MedGreen as we continue to speed towards becoming a fully operational site. As shown in the above video, some of our key building developments are really starting to take shape and we are 100% on schedule for harvest and production of our first season of beautiful New Zealand Cannabis flower.

Construction Progress:

  • Agriculture Processing & Manufacturing Facility (1000m2) - Due for completion May 1. Now 50% complete.
  • GMP Manufacturing Building (1000m2) - Due for completion Oct 1. Now 50% complete.
  • Production House 1 (1650m2) - Due for completion Apr 15. Now 50% complete.
  • Production House 2 (5,000m2) - Due for completion Aug 1. Now 25% complete.

MedGreen Construction Manager, Brendon Harris says, "the long periods of fine weather we've had lately has meant there's been no delays to our building programme. The team have taken advantage of this and we're set to make even more progress in the coming weeks".

With Production House 1 scheduled for completion by mid-April and our Processing & Manufacturing Facility finished by May 1, MedGreen will soon be processing and packing New Zealand Cannabis Flower and providing relief to patients in New Zealand and around the world.